PanOcean
Begins Construction of Onshore Pipeline in
Gabon
Pan-Ocean
Energy Corp. 10-18-2005.
Pan-Ocean www.panoceanenergy.com
says that
it has commenced construction of a wholly-owned and operated export pipeline
onshore
Gabon,
West Africa. The Company now expects the export pipeline to be completed and
onstream by the end of June 2006.

Onshore export pipeline
PanOcean is constructing a 26 kilometre, 10-inch diameter, crude oil export
pipeline from the Company's Obangue Field south to the Total-operated Coucal
facility. The pipeline is designed to transport all of the crude oil
production from the Obangue and Tsiengui fields (PanOcean 92.5% interest) as
well as production to be developed on the adjacent Awoun block (PanOcean
40%). The pipeline will be tied in to the Total-operated trunk line at the
Coucal facility, which in turn goes to the Total export terminal on the
coast at Cap Lopez.
Civil works for the pipeline right-of-way, started in early September, are
currently 40% complete and are expected to be finished by year-end. Pipe and
construction equipment are expected to be mobilised by the end of October
with installation and construction of the pipeline completed by March 2006.
The final component of the pipeline, a reheating, repumping and metering
facility adjacent to the Coucal processing facility, is expected to be
commissioned by June 2006. The export pipeline is planned to be fully
commissioned and in service by the end of June 2006.
Onshore drilling
PanOcean received and cleared the KCA Deutag drill rig through
Gabon
customs in mid-September. The rig is expected to be onsite to work over a
water injection well by early November. The rig is then scheduled to move to
the Tsiengui field and commence the Tsiengui development drilling program,
beginning with a water injection well on the south end of the field. The rig
is planned to continue drilling in the Tsiengui field through to the
completion of the current Tsiengui development drilling program.
On Awoun, the AWOCHE-1 exploration well was drilled by the Simpler 101 rig
to evaluate a sub-salt Gamba sandstone target to a total depth of 2,147
metres and logged. PanOcean's petrophysical analysis of well logs indicates
that the Gamba sandstone is water wet. The total Gamba Sandstone reservoir
thickness encountered is 57 metres (187 feet). The well is currently being
plugged and abandoned. The Simpler 101 rig will next move to the Merle
prospect to spud AWOMER-1, to the northwest of the Koula field |